Liquidated Damages is another important term discussed in construction contracts. Sometimes contractors misunderstand liquidated damages as a penalty for not completing the construction project within the stipulated time fame. However liquidated damages are not a penalty imposed on contractor. In this post I try to cover some of the details related to Liquidated damages including scenario to deduct liquidated damages from the contractor, reasons to deduct liquidated damages and employer’s rights for damages when the contractor does not complete the project as mentioned in the contract agreement.

Liquidated Damages in Construction Contracts

What are Liquidated Damages in Construction Contracts?

Liquidated Damages are pre-determined damages mentioned in the construction contract agreement which both parties to the contract agree as the amount to recover if the contract is breached. Usually Liquidated Damages are recovered by the Employer if the contractor fails to substantially complete the work within the stipulated time for completion.

Are Liquidated Damages penalties?

Liquidated Damages are not any penalties which imposed on contractors. It is a pre-determined amount to cover the possible loss that Employer has to face if the contractor doesn’t complete his work within the time for completion stated in the construction contract. Both contractor and employer knows the amount of Liquidated damages per day or per week if the work is not completed substantially. By signing the contract agreement, contractor agrees on the amount of Liquidated Damages that Employer can recover if the contractor fails to deliver the project within the Time for Completion.

Liquidated Damages in Construction Contracts

How to determine the amount of Liquidated Damages

While recovering of Liquidated damages occur at the completion of work scope in full or as a phase, the amount of liquidated damages are pre-set amounts depending on the size and nature of the project.

Amount of Liquidated Damages are determined based on the    possible loss incur to the Employer if the contractor fails to complete the project on time. These possible losses to the client include rental cost, loss of possible income if the project completed on time, extra running costs, temporary accommodation costs etc depending on the nature of the construction project scope.

Once these costs are identified, Liquidated Damages per day or per week is calculated. This is the amount mentioned in any construction contract as Liquidated Damages for the project. The amount can be per day or per week and it can be recovered if practical completion is not achieved for the whole project or a phase depending on the type of contract.

The amount of Liquidated Damages and the recovery period of it vary from project to project (or from contract to contract)

Reduction of Liquidated Damages

If the contractor fails to meet the practical completion by the mentioned project completion date, Employer is entitled to recover the Liquidated Damages from the contractor. Contractor shall allow the Employer to recover the liquidated damages calculated at the rate mentioned in the contract agreement for the period of delay.

However such recovery of Liquidated damages by the employer does not relieve the contractor from his liabilities and obligations under the contract. The contractor shall complete the project with accepted quality as per the contract.

For example, if the liquidated damages per day is $ 2000 and if the contractor’s substantial completion is 7 days delay then the employer is entitled to recover $14,000 as Liquidated Damages from the contractor. However the contractor still need to complete the project to the satisfaction of Employer and Engineer/Architect

So far I have experience in few projects that employer recovering liquidated damages from the contractor due to the delay in completion. These amounts are adjusted in the Final Account.

As a contractor you can check the possibility of EOT claims to avoid deduction of Liquidated Damages if you foresee delay in completion.

Extension of Time during Delay period

If the delay to the contract is due to a reason that contractor is not responsible, then the contractor has the right to request for Extension of Time. (EOT Claim) According to the construction contracts, there are several reasons that cause delay of the project and which are beyond contractor’s control. Some of such causes of project delay include Force Majeure, adverse weather conditions, industrial actions, instruction for a variation, Employer’s failure to give possession of site on time etc. If the project delay is due to such reasons that entitle the contractor to claim Extension of Time and if the Architect/Contract Administrator or the person authorized approve the extension of time then such time period is added to the total project period. This allows contractor to complete the work scope without any delay. However the contractor should apply in writing following the clauses in contract agreement when he finds the grounds for EOT claims.

Benefits of Liquidated Damages in Construction Contracts

Liquidated damages save both time and money. Although liquidated damages seems like beneficial for the Employer to recover his loss, this is a pre-determined rate which both parties agree at the time of signing the contract. Therefore both contractor and employer do not need to calculate the loss and damages if the project is delayed by 1 day.

However if the delay of the project is due to a reason that is beyond the contractor, he can claim EOT. Sometimes these reasons and scenario can create environment for disputes.

If you are a Main contractor and work with subcontractors to complete the project, then it is necessary to sign your contract agreement with the sub-contractor with necessary clauses. In the event that the delay is due to sub contracted work and if Liquidated Damages are mentioned in your sub-contractor agreement, then you can recover some part of liquidated damages from the sub-contractor depending on the project and contractual situation.